Row J1: Brickwork, and installation of door and window frames are in progress. |
|
Row J3: Structural work has been completed. |
|
|
|
Row K1: Tiling work and installation of roof tiles are in progress. |
|
Row K3: Brickwork, tiling work, installation of door and window frames and roof tiles are in progress. |
|